Hiring a pontoon for a machine: what do you check beforehand?

A hired pontoon often comes with a length and breadth in the brochure, but without the data you need to calculate the stability for your work. This article lists what to ask beforehand and what to record afterwards.

The short answer. Ask the owner for the dimensions, the weight, the hull shape, the position of the centre of gravity of the empty pontoon, the couplings and the permissible loading. Use these to calculate the stability for every phase of your work. Whoever puts the pontoon to use is, as a rule, responsible for the calculation for their own work and for the assumptions in it; what the owner must supply, and who arranges the certificate or the inspection, depends on the hire agreement and on the rules of the inspection body: agree that beforehand.

Which data do you need?

What do you calculate afterwards?

Calculate per phase of the work cycle, not one representative case: driving on board, working, slewing, hoisting, releasing. Check per scenario the heel and trim, the residual freeboard, the wind and the stock on the deck. The limits come from ES-TRIN chapter 22: Article 22.07(1) (the sum of the angles of heel and trim must not exceed 10°), Articles 22.04 and 22.05 (residual safety clearance and residual freeboard; a smaller residual freeboard only under Article 22.08) and Article 22.07(5) for the wind (0.25 kN/m²). National requirements may be stricter. Read more in stability requirements for floating equipment under ES-TRIN and inspection of floating equipment.

Questions to ask the owner

Who is responsible for what?

A calculation is evidence, not a verdict. Whether an assembly is accepted is decided by an expert or the competent authority. Whoever puts the pontoon to use is, as a rule, responsible for the calculation for their own work and for the assumptions in it. What the owner must supply in the way of data and properties of the pontoon, and what the owner is liable for, depends on the hire agreement and on the law: agree that beforehand. Who arranges the certificate or the inspection of the assembly (the owner or you as the user) depends on the agreements and on the rules of the inspection body or the competent authority; an inspection often applies to the configuration as a whole, so make that clear beforehand. Data from a brochure or a library may be incomplete or out of date: check it yourself with the owner before you work with the calculation. This is information, not legal advice.

How StabCal approaches this

StabCal™ has a library of pontoons and machines and lets you add your own data. Every weight and every centre of gravity states its source, and an assumption is marked as an assumption. In StabCal you confirm that you understand that the data may be incomplete or out of date and that you must check the current data yourself with the owner or manufacturer. See also why the lift chart is not enough for an excavator on a pontoon.

StabCal checks, per scenario, the criteria from ES-TRIN 2025/1 chapter 22 that are built into StabCal, as far as StabCal can calculate them. Whether an assembly of pontoons is accepted in your situation is decided by an expert or the competent authority; national requirements of the country or of the competent authority may be stricter. StabCal does not give an approval, a declaration of conformity with ES-TRIN or a proof of stability within the meaning of Article 22.07 paragraph 2; a StabCal calculation can form part of that proof. For wind, StabCal uses the specific wind pressure of 0.25 kN/m² under Article 22.07 paragraph 5, with the shape-dependent coefficient of resistance 1.6 (the value for solid-section structures) for all surfaces, and in 24 wind directions instead of only athwartships; that is not more favourable than that paragraph. The safety clearance to openings you do not specify, the tipping stability of the machine, deck pressure, couplings, ground contact and waves are outside the calculation.

Sources

Frequently asked questions

Which data do you ask for when hiring a pontoon for a crane or excavator?

Dimensions of the deck and the hull, the weight of the empty pontoon and the position of the centre of gravity, the couplings, the permissible loading of the deck, the openings to the interior and any earlier calculations or certificates with the configuration for which they were made.

Is the owner responsible for the stability of the hired pontoon?

Whoever puts the pontoon to use is, as a rule, responsible for the calculation for their own work and for the assumptions in it. What the owner must supply in the way of data and properties of the pontoon, and what the owner is liable for, depends on the hire agreement and on the law: agree that beforehand. Who arranges the certificate or the inspection of the assembly depends on the agreements and on the rules of the inspection body or the competent authority. This is information, not legal advice.

Does the stability of a hired pontoon with a machine have to be calculated?

For a pontoon with a crane or hydraulic excavator as floating equipment, ES-TRIN as a rule requires a proof of stability (chapter 22, Article 22.07; exceptions (Article 22.10) and national rules exist). Which requirements apply in your situation, and who assesses them, is decided by the inspection body or the competent authority.

Read more

Last updated 22 November 2026. StabCal is a tool for work preparation; this article contains general information and is not legal advice or advice for a specific project.